Waitsia Gas Project Stage 1

AWE LIMITED | Western Australia

Overview

The project expanded the processing capacity of the existing Waitsia Gas Facility (Xyris Plant) through the addition of Boost Compression, new processing equipment and additional power generation.

The scope of the project included a connection to the existing Waitsia 2 wellhead , requiring a new flow line and wellhead facilities.

The previous connection to the PGP was also isolated and a new sales gas connection to the DBP was provided, including a new 4km AS2885 Pipeline.

The project is currently in commissioning and is due for completion in August 2020.

 

Project facts

SCOPE

  • New Flowline and well connection
  • 4km DN350 As2885 Pipeline
  • Pipeline Facilities
  • Power Generation and Gas Processing
  • New Compression

CLIENT

  • AWE Limited

LOCATION

  • 14.5 kilometres east of Dongara and 367km north of Perth, Western Australia

DATES

  • Jun 2019 to Aug 2020

ROLES & SERVICES

  • Concept and FEED: Engaged by AWE to develop the concept engineering package and complete the front-end engineering and design. Subsequently engaged to deliver project including execution planning, contract and procurement packages, cost estimate and schedule sufficient to support project FID
  • EPCM: Engaged by AWE as the EPCM contractor for delivery of the project
  • Commissioning: Engaged by AWE to perform commissioning and assist with handover to operations

KEY CHALLENGES

  • Brownfields construction management
  • Maintain project site progress during COVID-19 Pandemic